Building process

December, 23

December, 23

December, 9

December, 9

1. Fencing around the reinforcement shop is in the progress.
2. Assembling of windows has begun.
3. Planning of the domestic building has begun.
4. The interior trim of the domestic building.

October, 29

October, 29

October, 12

October, 12

1. The construction of the 4th floor of the domestic building.
2. The construction of the partition of servicing metal centre for gauge unit has begun.
3. The levelling of sand in servicing metal centre was finished.
4. The sanding of the reinforcement shop was finished, strewing with crushed stone of the foundation of the reinforcement shop has begun.
5. The construction of the domestic buildings in the reinforcement shop has begun.
6. The construction of the fence on the right side of the territory was finished.
7. The levelling of the sand foundation on the right side of the territory was finished and strewing with crushed stone of the foundation has begun.
8. The laying on all 4 turns of the water supply system, the fire line, the sewerage system and rainwater disposal.
9. The construction of the check point № 1 (entry on the base) has finished, foundations, sanding on entry are ready and strewing with crushed stone has begun.

September, 21

September, 21

1. The carrying over water supply system about 470 meters of Kalinin Factory from the territory of the base «STEEL-Trade» has finished.
2. The ceiling of the second floor has finished and the construction of the third floor of the domestic building is in the process.
3. Foundations of the check-point № 1 (entry and departure) have been built.
4. Foundations of the administrative building have been built on 100 % and the filling has begun.
5. The rework of concrete and brick (from dismantling) in crushed stone has begun. We plan to get 5 000 – 6 000 cubic meters of product.

September, 8

September, 8

1. The production and installation of brake girders on crane-running beams in the service metal centre has begun.
2. The pile field has prepared and the filling of grids of administrative building has begun.
3. The brickwork of the second floor is at the end.
4. The territory in 6 ha is strewn with sand and layerwise rammed.
5. Crushed stone is being strewn and rammed now on the territory.
6. The territory under the construction of the checkpoint № 1 with weigh station and the central entry on the production base has been prepared.
7. 350 meters of inside railway for installation and fastening have been prepared.
8. The agreement was concluded to the remaking of breakage of ferroconcrete items that were formed during the dismantlement that are going to be used for strewing of inside work.

August, 25

August, 25

August, 11

August, 11

August, 4

August, 4

Jule, 28

Jule, 28

Jule, 19

Jule, 19

Jule, 5

Jule, 5

June, 25

June, 25

June, 6

June, 6

May, 24

May, 24

May, 17

May, 17

May, 3

May, 3

April, 25

April, 25

April, 18

April, 18

April, 6

April, 6

In future

In future